Building plans are nearing completion on all the details, with most of that work behind the scenes. Looking ahead, this winter visible construction will get underway (fingers crossed), continuing through spring and into summer.
As the build-out wraps up, we’ll need time to get everything ready to open to the public, ideally around early fall 2027.
MILESTONES
> [DONE] Feasibility research, site selection, property purchase, conditional use permit approval, design development
1. [TARGET: late Oct.] Bowling equipment: select supplier & installer, sign contract. We're near completion of this.
2. [TARGET: late Oct.] Building plans: finalize construction plans, engineer all systems, estimate costs, adapt plans to budget, and submit to the city for review. We're near completion of this.
3. [TO-DO] Building permits: work through reviews, address all comments and revisions.
4. [TO-DO] Demolition: remove everything that isn't being reused. Targeting start before the end of 2026.
5. [TO-DO] Construction: build it! Targeting January 2027 start.
6. [TO-DO] Recruiting & hiring: start top-down with a likely general manager role, early 2027.
7. [TO-DO] Licensing etc, including planned beer & wine service, in parallel with build-out.
8. [TO-DO] Approval to operate: certificate of occupancy, all licensing and pre-reqs complete.
9. [TO-DO] Pre-opening: staffing, training, test runs, etc.
10. [TO-DO] Soft open, then fully open. Targeting September-October 2027.
Sharing a projected timeline is a great way to jinx it and fall behind. But on balance the aim is to be transparent about what's happening along the way on a big vacant corner in town.
Q&A
When will it open?
// Targeting September-October 2027 currently. Realistically timelines more often slip later vs. finish earlier than planned. It’s a goal, not a promise.
How many lanes?
// 12. Full regulation length, synthetic approach and lane surfaces, to be USBC-certified.
What kind of pinsetter machines, free-fall or strings?
// Strings. USBC-certified state-of-the-art variety with competition vs. recreation modes. Much love and respect for the old workhorse machines, some bowlers' strong free-fall preference is seriously considered. But realistically strings can be the difference between alleys surviving or not nowadays.
Less down-time, maintenance, electricity use, and mechanical complexity are the advantages on cost and pricing. With the goal of bringing bowling back here, introducing new generations to it, and sustaining it for decades, the balance on pros/cons was pretty clear.
Liquor license?
// Planning on beer & wine service, alongside a full commercial kitchen and restaurant service.
Will there be an arcade?
// Yes, both kid- and adult-geared game areas. Details are still TBD within those areas.
Will there be leagues?
// Yes, planning on it, though not deep into details yet. Balancing time and space for leagues, events/reservations, and open bowling will be important once we get started.
Will El Niño disrupt construction?
// TBD! Most construction work is indoors, luckily.
How's it been working with the city?
// So far so good. “No surprises” has been our approach, so everyone involved can think ahead on potential issues before we run into them.
When will you be hiring?
// See milestones above. Most roles wouldn’t be hired until closer to opening in 2027.
How can we help?
// It’s a little premature to dive all the way into these, but putting the ideas out there:
- If you're experienced/interested in organizing a league, it'd be good to chat!
- If you’ve got old photos of good times bowling in or around Mendocino County, we’ll have a couple of places for community contributions to bring local memories into the new space.
- If you’re an artist or muralist who’d be interested in potentially livening up the space with local artwork, please reach out.
As other opportunities for involvement come up, we’ll share here. Feel free to reach out any time with other thoughts or input.
Up next:
Complete building plans
Equipment, furniture and interior choices
Architectural details example, one of many parts of building plans.